MPs have demanded that the head of Kiira Motors Corporation explain why buses made at its Jinja plant cost so much more than imports from Europe and elsewhere.
The legislators, who sit on Parliament’s Committee on Commissions, Statutory Authorities and State Enterprises (Cosase), raised the issue during an on-the-spot visit to the corporation’s headquarters in Jinja, where they learned that one bus can cost up to Shs 1.2 billion.
The visit followed an earlier meeting between Kiira Motors officials and the committee. That meeting looked at queries raised in the Auditor General’s report for 2024/25, and the MPs agreed a site visit was needed.
The chief executive, Paul Isaac Musasizi, led the MPs around the factory.
Martin Muzaale, the MP for Buzaaya, asked Musasizi to justify the price tag.
“Mr CEO, the buses are too expensive. What is the business model here compared to other buses that are imported?” he said.
Hakim Kizza, the MP for Bukoto South, asked whether the project would ever turn a profit, given the sums already spent on it.
“I want to know when the corporation will break even, given the amount of money so far injected into the project,” he said.
Other MPs asked whether the corporation would meet its production targets.

Musasizi defended the cost of the buses. He said prices could fall if the plant built more of them.
“There is room for us to bring down these production costs by increasing the volumes of manufacture,” he said.
“Our prices are lower compared to a brand-new bus from Europe. That is why we have attracted clients outside Uganda. They take the deal after realising that ours is a better deal.”
On the question of breaking even, he said the corporation must build far more buses than it does now.
“We need to be producing 520 buses every year to break even,” he said.
The government has so far put more than Shs 600 billion into the corporation. Since it began work, Kiira Motors has built 115 buses.
Musasizi told the MPs the plant is short of workers. He said the production line needs 900 people to meet demand, but the corporation has only 120.
He said the plant was operating at 95% by 2025 and is now at 100%.
At present, the corporation can build three buses a day. Its target is 11 buses a day.