MPs have demanded answers from the Minister of Works and Transport, Fred Byamukama, on why the multibillion-shilling Standard Gauge Railway (SGR) has still not started on the Ugandan side.
They raised their concerns during a plenary sitting chaired by the deputy speaker, Thomas Tayebwa. Byamukama had come to update the House on the project.
The first phase is the 272km line from Malaba, on the Kenyan border, to Kampala. Uganda signed the deal for it in 2024 with the Turkish firm Yapı Merkezi, but work has been slow.
Asinansi Nyakato, the Hoima City woman MP, asked why people affected by the project had not been paid. She is the shadow minister for works and transport and belongs to the People’s Front for Freedom (PFF).
She said late payment was driving up the project’s cost. She also wanted to know how much had been set aside for climate and environmental risks.
Gerald Karuhanga, the Ntungamo Municipality MP, compared Uganda with its neighbours. He said Tanzania had built about 460km of its line and Kenya about 500km. Uganda’s 272km stretch was still waiting, he said, and he asked why work had not begun.
Janeth Ayoo Obol, the Gulu District woman MP, asked whether Ugandans were being trained so that local people would benefit from the project.
Abdul Bisaso, the Kassanda County South MP, said officials of the Uganda Railways Corporation had pulled down houses in his constituency without notice. He asked the minister to send surveyors to mark the boundary and clearly show where the railway land ends.
Dennis Alyela Omodi, the Lira City East MP, said some houses had been marked even though they lay outside the railway reserve. He asked for a clear compensation plan that would resettle his people.
Byamukama told the House that the government’s priority was the 272km Malaba to Kampala section. He said it fully backed the wider link to the Northern Corridor, the main trade route to the port of Mombasa.
He said the project needed about Shs12.3 trillion over a four-year contract period. The appraisal of those affected by the project was complete, he said.
So far, he said, the government had paid Shs373 billion to 7,700 people. He put the number still to be paid at about 5,200, who are owed Shs472 billion.
Byamukama admitted that getting land along the route was still a problem. He said the government was working with the Ministry of Energy and Mineral Development to put the supporting infrastructure in place.
On climate and environment, he said Shs11 billion had been set aside to protect the environment. He said the figure could go up if needed.
He promised that work would start as soon as the finance ministry released the money. The government has said it hopes to reach financial close on the project in January 2027.
On Kassanda, Byamukama said the demolished buildings stood inside the railway reserve. He said removing them would save the government compensation money. He agreed to send surveyors to open the boundary.